A MAJOR road maintenance scheme in Eden has reached completion ahead of schedule.
Cumbria County Council has now finished its highway improvement works project on the A686 at Meathaw Hill near Alston.
Works started on Tuesday, September 1 with a proposed schedule of five weeks for the scheme.
However, due to the mild and dry weather recorded last month, the works were completed in four weeks, the council said, 'resulting in less disruption and inconvenience for road users'.
This final stage of resurfacing works completes an investment of approximately £1.8m and is the final stage of a four-year programme of a highway improvement works scheme on the A686, which has also included drainage improvements.
In total, approximately 9.5km of the A686 has been resurfaced, with associated drainage improvements during the last four years.
Commenting on the work, Cllr Claire Driver, Cumbria County Council’s Local Member for Alston and East Fellside, said this week: “I’m so pleased that we were able to get these works completed more quickly than thought.
"This has meant less disruption for local people, and helped relieve the pressure on business affected by the closure.
“The local community has worked together to promote the town throughout the improvement works, which will benefit communities around Alston for years to come.
"A big thank you to all of the teams involved for their efforts to get these works completed ahead of schedule.”
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules here